Last week

Rear slab kongo'd to rubble

Rear slab kango’d to rubble

Door relocated from third floor to our new en-suite

Door relocated from third floor to create new doorway to our new en-suite

Roof space opened up

Roof space opened up

Door relocated on third floor... nice big office for Pete!

Door relocated on third floor… nice big office for Pete!

Site shoes

Site shoes !

Week two

Scaffolding up on rear facade

Lower ground floor wall opened up

Our very our steel beam!

Rear outhouse largely demolished

Scaffolding, steelwork and enabling works well underway… these guys don’t mess around!

Week one

Ceilings down, hello headroom!

Ceilings down, hello headroom!

Down to the chalk

Down to the chalk

Bathrooms away!

Bathrooms away!

Goodbye old kitchen

Goodbye old kitchen

We will put something much better back!

We will put something much better back!