Last week Posted on July 31, 2013 by Helen 0 Rear slab kango’d to rubble Door relocated from third floor to create new doorway to our new en-suite Roof space opened up Door relocated on third floor… nice big office for Pete! Site shoes !
Week two Posted on July 8, 2013 by Helen 0 Scaffolding up on rear facade Lower ground floor wall opened up Our very our steel beam! Rear outhouse largely demolished Scaffolding, steelwork and enabling works well underway… these guys don’t mess around!
Week one Posted on July 2, 2013 by Helen 0 Ceilings down, hello headroom! Down to the chalk Bathrooms away! Goodbye old kitchen We will put something much better back!